Title: Line of balance application on a residential building
Authors: Dandashi, Abdul Rahman
Eid, Abdul Kader
Advisors: Omran, Mazen Nazem
Subjects: House construction
Line of balance (Management)--Case studies
Issue Date: 2015
Abstract: 
In fast tracked project, a start to start relationship with lag is used between the construction activities when scheduling the total project activities. This may result in delays and additional cost due the presence of different crews in the same space due to the different rates of production. This problem cant be illustrated in Critical Path Method (CPM) method as such as primavera software. A line of balance analysis is required to detect such problems and purpose proper mitigation measure. For that a study case analyses have been done to explain and examine this problem to give suitable and innovative solutions to reduce as much as possible the money and time loss.
Description: 
Includes bibliographical references (p. 58).

Supervised by Dr. Mazen Omran.
URI: https://scholarhub.balamand.edu.lb/handle/uob/2886
Rights: This object is protected by copyright, and is made available here for research and educational purposes. Permission to reuse, publish, or reproduce the object beyond the personal and educational use exceptions must be obtained from the copyright holder
Ezproxy URL: Link to full text
Type: Project
Appears in Collections:UOB Theses and Projects

Show full item record

Record view(s)

45
checked on Nov 22, 2024

Google ScholarTM

Check


Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.