Title: | Line of balance application on a residential building | Authors: | Dandashi, Abdul Rahman Eid, Abdul Kader |
Advisors: | Omran, Mazen Nazem | Subjects: | House construction Line of balance (Management)--Case studies |
Issue Date: | 2015 | Abstract: | In fast tracked project, a start to start relationship with lag is used between the construction activities when scheduling the total project activities. This may result in delays and additional cost due the presence of different crews in the same space due to the different rates of production. This problem cant be illustrated in Critical Path Method (CPM) method as such as primavera software. A line of balance analysis is required to detect such problems and purpose proper mitigation measure. For that a study case analyses have been done to explain and examine this problem to give suitable and innovative solutions to reduce as much as possible the money and time loss. |
Description: | Includes bibliographical references (p. 58). Supervised by Dr. Mazen Omran. |
URI: | https://scholarhub.balamand.edu.lb/handle/uob/2886 | Rights: | This object is protected by copyright, and is made available here for research and educational purposes. Permission to reuse, publish, or reproduce the object beyond the personal and educational use exceptions must be obtained from the copyright holder | Ezproxy URL: | Link to full text | Type: | Project |
Appears in Collections: | UOB Theses and Projects |
Show full item record
Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.